Management of risk associated with intermediate train stop installation
Date issue released
Safety Issue Description

Sydney Trains' risk management procedures did not sufficiently mitigate risk to the safe operation of trains in circumstances where the presence of an intermediate train stop at Richmond may have reduced the risk of trains approaching the station at excessive speed.

Issue number
RO-2018-004-SI-04
Issue Status
Open – Safety action pending
Transport Function
Rail: Infrastructure
Issue Owner
Sydney Trains
Mode of Transport
Rail
Issue Status Justification

The ATSB notes that the signalling upgrade and the introduction of ATP, once implemented, should address the safety issue.

Proactive action
Action number
RO-2018-004-NSA-019
Organisation
Sydney Trains
Action date
Action Status
Closed
Action description

Sydney Trains have completed a signalling upgrade at Richmond, including intermediate train stops to control the approach speed. As well, implementation of the ATP project will control the risk of overrun incidents using engineering controls to supervise the train speed and enforce braking when necessary.