The insulated rail joints were incorrectly placed
Date issue released
Safety Issue Description

The placement of the insulated rail joints adjacent to signal DYN150 was not in accordance with the ARTC engineering procedure ESC-07-01.

Issue number
RO-2013-020-SI-01
Transport Function
Rail: Infrastructure
Issue Owner
Australian Rail Track Corporation
Mode of Transport
Rail
Issue Status Justification

The ATSB is satisfied that the action taken by the ARTC addresses this safety issue.

Proactive action
Action number
RO-2013-020-NSA-097
Organisation
Australian Rail Track Corporation
Action date
Action Status
Closed
Action description

Within Victoria, the Australian Rail Track Corporation initiated a survey to measure and record the position of insulated joints relative to the position of the signal to which they refer. Sites where the maximum specified distance was exceeded were entered into a risk-based and prioritised remediation plan.