The quality assurance processes used in the acceptance of the Goddards crossing loop project were not sufficiently robust to mitigate the risk of track construction inadequacies.
SAN only requires ARTC to consider the implications of this safety issue and take action where considered appropriate.
The Australian Rail Track Corporation has advised that it will reinforce its project management and audit processes, as outlined in its Project Management Procedure (PP 157), with its employees, in particular the requirement for:
Satisfactorially addressed by the ARTC