Quality control process
Date issue released
Safety Issue Description

The documentation and quality control processes used by the South Improvement Alliance for the Cootamundra re-signalling project were not sufficiently robust, in particular, the closing out of identified design issues was inadequate.

Issue number
RO-2009-009-SI-03
Transport Function
Rail: Infrastructure
Issue Owner
Australian Rail Track Corporation
Mode of Transport
Rail
Issue Status Justification

THe ARTC has introduced additional verification processes to record design changes changes in the works. The ATSB has reassessed the risks associated with this safety issue and while there is still a risk of injury, the ATSB believes the responses provided by the ARTC and RailCorp adequately address this safety issue.

Proactive action
Action number
RO-2009-009-NSA-025
Organisation
ARTC
Action date
Action Status
Closed
Action description

The Australian Rail Track Corporation has advised that the following actions will be taken with respect to future signal design work. A standard process to be nominated for raising recording and resolving all issues that arise during the design process. The record to form part of the Design Verification. Include in the Signal Design Process a record of signal design staff against activity against version.

ATSB Response

The Australian Transport Safety Bureau is satisfied that the action taken by the Australian Rail Track Corporation adequately addresses the safety issue.