A record of the welds carried out at the 8.351 km point at Tottenham on the 30 January 2009 was not documented in accordance with the requirements of Civil Engineering Circular 3/87.
The ARTC have not provided a response to this minor safety issue prior to publication of the final report. ARTC have advised that a response will be provided in due course.
The Australian Transport Safety Bureau advises that the ARTC should consider the implications of this safety issue and take action where considered appropriate.