Measurement of rail creep
Regular monitoring and accurate measurement of rail creep was not carried out at the east end of the curve where train 6MB2 derailed in accordance with Civil Engineering Circular 3/87 - 70.2 and 70.3. Creep monuments were not installed on the east end of the curve following the work to convert the passing loop track to mainline operation in July 2008.

Safety Advisory Notice
The Australian Transport Safety Bureau advises that the ARTC should consider the implications of this safety issue and take action where considered appropriate.